Follow the evolution of the ZIN project closely.
Through this page we will keep you informed about the most important milestones of the project.
Project timeline
2017
Belgian architecture competition
In 2017 Befimmo made a call for applications for the redevelopment of the WTC 1 & 2 building. Befimmo chose the architectural team of 51N4E, Jaspers Eyers Architects and l’AUC for the design.
Participation of Befimmo in Flemish government public contract
Befimmo participated with its ZIN project in the public tender for works that was launched by the Flemish authorities.
Temporary occupation of WTC 1 and co-creation process
Befimmo made the vacant WTC 1 tower temporarily available to a number of organisations (universities, architects, start-ups, library, artists, etc.). They focused on a single aim: contributing to the project to reshape the North area.
The construction team of ZIN was also assembled on a floor of the existing WTC 1 tower during the design phase, which ensured a unique co-creation process in which connection to the environment was a central focus.
2018
Application for the building and environmental permit
In June 2018, Befimmo submitted the applications for the redevelopment of the WTC 1 & 2 towers to the Brussels Capital Region.
End of the ongoing lease in WTC 2
2019
Start of phase 1 works
Start of the cleaning and asbestos removal work.
Offices pre-let to the Flemish authorities
In March 2019, Befimmo obtains the public tender of the Flemish authorities. As a result, the 75,000 m² of offices of the ZIN project have been fully pre-let.
2020
Building and environmental permits obtained
In March 2020 the building and environmental permits were delivered to Befimmo.
Start of phase 2 works
Start of the dismantling works on the towers. One floor is being dismantled per week, for 30 weeks. Only the cores are being kept.
2021
Start of phase 3 works – the actual construction
The two towers are being rebuilt and connected by a new central volume.
2023
Delivery of building – Start of the public tender of the Flemish authorities
The Flemish authorities begins its lease in the building for a fixed period of 18 years.