MagaZIN – newsletter November 2021
MAGAZIN
ONLINE EDITION
November 2021
ABOUT ZIN
ZIN is the project to transform Towers 1 and 2 of the WTC complex in the Brussels North area. This emblematic project is the first in the North area to combine different functions in a highly innovative way.
First stone of the Marie-Elisabeth Belpaire building
Besides flats and a hotel, the ZIN project consists of 75,000 m² of new office space for the Flemish government. These 2,400 new workspaces for 4,750 employees are located in the new central volume that connects both towers. On 7 October, the first (symbolic) stone was laid and the new name (Marie-Elisabeth Belpaire building) of the office building of the Flemish government was unveiled in the presence of Flemish Prime Minister, Jan Jambon and Flemish Minister for Brussels Youth and Media, Benjamin Dalle. Befimmo (together with the Flemish government) is fully committed to circularity and sustainability. Curious on how the day went? Find more information here.
By Jan Jambon
Minister-President of the Government of Flanders and Flemish Minister for Foreign Policy, Culture, Digitization and Facilities
” The first stone of the Marie-Elisabeth Belpaire building has been laid. This new prestigious office building in the North area of Brussels will be a real landmark in Brussels! A fine example of modern and sustainable building.
From rubble to new, high-quality concrete
Are you curious to know how the rubble of the old WTC towers is being turned into high-quality concrete and will be (re)used in the ZIN project? Follow the trip of circular concrete within a 15km radius.
Iconic hotel The Standard opens in ZIN (2025)
Lifestyle hotel pioneer The Standard is moving into the ZIN project. With 180 rooms and 20 flats, it will welcome its guests in Brussels as of 2025. Together with the other functions of ZIN, the hotel will contribute to a new dynamic in the Brussels North area.
From WTC 1 & 2 to ZIN in 5 stages
Stage 01: Application for and issuance of permit
Stage 02: Preparatory work, cleaning and asbestos removal
Stage 03: Dismantling of towers
Stage 04: Construction of central volume, reconstruction of towers, and completion – from April 2021
Stage 05: Building delivery – summer 2024: complete commissioning
More information?
We’ll be happy to help you with any questions or comments about the ZIN project. Contact us online via mail.